Expansion● Neutral for Indian equities

Oracle invokes force majeure over power delays at New Mexico data-centre project

6 sources · first seen 21:40 24 Sept · updated 15:00 25 Sept

The brief

Written from 6 reports · check the source before you trade
  • Oracle shares fell 5% in one report and 3% in another
  • The project faces power delays, local resistance and the removal of a development partner
  • Oracle may delay payment if the data centre is not operational in 2028

Tags on this story

Pick a tag to see all its stories

Linked by the tag New Mexico

6 stories this week
  1. 25 SeptCalifornia’s New, Less Powerful Reality1 source
  2. 24 SeptNew Mexico privacy trial against Facebook goes to jury, with billions in penalties at stakeLegal · 2 sources · Jurors must decide whether Facebook violated New Mexico's Unfair Practices Act and how many times
All New Mexico stories →
Part of a developing story5 updates over 2 days

Oracle’s New Mexico data centre delays

Oracle issued a force majeure notice over power delays at its Project Jupiter data centre in New Mexico, seeking protection from potential cost increases. The development raised concerns about AI infrastructure financing and weighed on Oracle Financial Services Software shares.

Read the reports

6 reports · earliest 21:40
Hindustan TimesWhy Oracle shares fell 5% over New Mexico data center cost concerns21:40TechCrunchOracle sends force majeure notice on its New Mexico Stargate data center23:41CNBCOracle sends 'force majeure' notice about data center project — stock drops 3%01:30ReutersOracle triggers 'force majeure' on data center project over power delays, source says04:30CNBC-TV18Oracle triggers 'force majeure' on data center project over power delays: Report07:44WSJCracks in Oracle’s AI Data-Center Build-Out Appear in Massive New Mexico Project15:00